DEPUTY MAYOR OF BOGOR REVIEW WORK ON CONSTRUCTION OF BOGOR- SUKABUMI DOUBLE TRACK
Microsoft Office Translator
Bandung –. Deputy Mayor of Bogor, Dedie A Rachim accompanied by the Head of Public Works and Spatial Planning Office (PUPR), Chusnul Rozaqi, South Bogor Sub-District Hidayatullah and Head of The Railway Engineering Center of West Java Erni Basri and the ranks reviewed one of the National Strategic Projects (PSN), The Construction of The Double Railway Railway Paledang Segment – Cicurug.
"Currently some buildings in the Batutulis area have begun to be demolished. The demolition was carried out to support the arrangement in the area. Said Dedie after reviewing the location of the double track work, Tuesday (9/3).
According to him, Batutulis area is a crucial point for the city of Bogor. So that between the Bogor Municipality and the West Java Railway Engineering Center must perform various synchronizations.
"This synchronization includes setting up a path or access path, which we may have to slide. And as long as it may still be clustered with Batutulis station then in the future in one year, we have to think of a road engineering,"
So, some workmanship in Batu Tulis Station can have more opportunities to be developed and built with new facilities. For example, the construction of power houses, new fly overs, and so on." Then, we will also do some kind of coordination with the central government. In this case with Bappenas and the Ministry of PUPR which will be right next to Batutulis Palace," he said.
Accompanied by the Head of The Railway Engineering Center of West Java Region, Erni Basri explained that there are 713 areas of land that have been paid. With details, 517 fields are located in Empang Village and 196 fields in Batutulis Village.
If the last 713 was clear all, the value of the material was the last week Rp 15.7 Billion. People were very grateful and they were very happy," said Erni.
Erni said, in this week, the rule should be completed. Thus, the Railway Engineering Center can put tools and materials on the construction site so that the work can be continued immediately.
I think if the impact, from the local government has provided synergy how to regulate citizens and citizens manut only, Temporarily on average they alhamdulillah occupy state land. For the progress of bogor-sukabumi double track development bogor paledang segment - Cicurug itself has now reached 75 percent he said.